| - June 24, 2006...The finishing touches.. |
| - June 7, 2006...MU Hockey team helps replace sidewalk.. |
| - April 23, 2006...The DEDICATION!! |
| - April 22, 2006...Adding the final touches... |
| - April 15, 2006...The driveway is formed up... |
| - April 8, 2006...The last of the siding goes up... |
| - April 1, 2006...Starting to wrap things up...at least on
the outside... |
| - March 25, 2006...MU chapter of Habitat cleanup time and
hanging siding |
| - March 18, 2006...Installing door hardware |
| - March 4, 2006...Hanging the doors and on the windows begins! |
| - February 25, 2006...Cleaning and painting begins! |
| - February 11, 2006...Drywall hung in one day! |
| - February 4, 2006... Insulation completed! |
| - January 28, 2006...Inside
and outside work. |
| - January
21, 2006...Key Club members and others help Insulate
house. |
| - January
14, 2006...Preparing for cabinets to be installed. |
| - January
7, 2006...The interior wiring and misc. projects continue. |
| - December 17, 2005...Seabee Veterans and local chapter members
get more work done.. |
| - December 3, 2005...Christ Church at Mason Youth Group,
Talawanda Key Club members and several members of the Oxford
chapter were not deterred by the cold weather. Tyvek installation
was completed and taped; windows are taped and the siding started
to go up. |
| - November 19, 2005...Talawanda Key Club members to the rescue... |
| - October 22, 2005...The house is all "buttoned" up... |
| - October 15, 2005...Oxford
Chapter folks have a productive day... |
| - October
8, 2005...MU Habitat Chapter |
| - October
1, 2005...MU Habitat Chapter, Club Hockey team & Cornerstone
United Methodist youth group |
| - September
24, 2005...MU Women's Swim Team come to the rescue |
| - September
17, 2005...Campbell Soups Sales lends a helping hand... |
| - September
10, 2005...Square D lends a helping hand... |
| - August
27, 2005...More work on the second floor. |
| - August
23, 2005...The trusses go up! |
| - August
13, 2005...some finishing touches... |
| - August
6, 2005...rain delay! |
| - July
30, 2005...all the 1st floor walls completed |
| - July
23, 2005...the progress continues... |
| - July
16, 2005...the first wall goes up... |
| -
July 9, 2005 |
| -
July 2, 2005 |
| -
Foundation wall forms |
| -
Digging the foundation and footer pictures |
| -
Ground breaking pictures |